Third Mainland Bridge to be totally shut down this weekend

The Federal Government has announced the completion of the first phase of rehabilitation of the Third Mainland Bridge.

There will also be an 18-hour total closure of the bridge this weekend.

The Federal Controller of Works in Lagos, Olukayode Popoola, during an inspection of the bridge noted that the fixing of six expansion joints on the Oworonshoki-bound carriageway had been completed.

Popoola said the closure was necessary, so that debris would be cleared from the section and construction would move to the Island-bound carriageway.

The 18-hour closure would begin from midnight on Saturday through Sunday. By midnight of Sunday, the total closure would be removed and the partial closure would return.

Advertisement

“The diversions will still be at the same previous points.

“Work is to commence on the Island-bound lane of the bridge with the partial closure of Adekunle to Adeniji Adele Phase B.

“The repair work is to commence between 22nd of November, 2020 and 22nd of February, 2021 for a duration of three months,” he said.

Signature TV
Signature TVhttps://signaturetv.isitedigitals.com
Signature TV is a multi-media company, owners and operators of signaturetv.org and producers of The Signature Show on AIT and Corruption Tori. Our programmes are broadcast on the AIT Network and on Seven NTA stations across the country. We are content providers for a number of television networks and some State TV stations, with a respected 24/7, high online and offline followership. We are also Communications/Media Consultants to MacArthur Foundation, Ford Foundation and OSIWA.

Related Articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here
Captcha verification failed!
CAPTCHA user score failed. Please contact us!

Latest Articles